Starting from October 2021, the project by Thanh Cong as the general contractor has been seriously constructed and completed on time for handover. After more than 5 months of construction and completion, Thanh Cong ME Construction JSC has officially handed over the project to Toyota Motor Vietnam.
The project "Moving the welding workshop power station" is one of the key projects of Thanh Cong at the end of 2021 with extremely strict requirements for quality and technique of the Investor. Construction during the transition period from the end of the year to the end of the Lunar New Year and before the complicated developments of the Covid-19 pandemic, construction, implementation and application of many prevention and control measures to repel the epidemic, ensuring the construction items take place on schedule, with quality, safety and aesthetics.
By the afternoon of March 23rd, 2022, all preparations were completed and ready for acceptance.
On March 24th, 2022, Thanh Cong's leadership and project management team together with Toyota conducted the acceptance test of the project.
In the meeting after the actual acceptance, the Board of Directors of Thanh Cong directed the Project Steering Committee to draw lessons from experience and especially thank the entire Project Management Board for their hard work and successful completion. assigned work to complete the project on time.
With all the dedication of a team of talented and enthusiastic engineers, after more than 5 months of construction, the project has brought satisfaction to the Investor. Along with the quality, progress and safety that are fully met during the construction process, this is also a step forward for Thanh Cong to continue to conquer large-scale projects with strict technical requirements of the Investors.